Building · Compliance

Compliance calendar

Statutory and safety obligations, aligned to the RICS Service Charge Residential Management Code (4th ed.). Reeve flags what's due and drafts the instruction.

3 items need action

Reeve can draft the instruction to each contractor — you review and send.

OverdueCommunal gutter clearancedue 1 Apr 2026 · 69 days overdue
Due soonLift LOLER inspectiondue 25 Jun 2026 · in 16 days
Due soonFire alarm servicedue 2 Jul 2026 · in 23 days

On track

8

Due soon

2

Overdue

1

Not applicable

1

ObligationFrequencyLast doneNext dueStatusContractorRICS
Communal gutter clearanceAnnual1 Apr 20251 Apr 2026OverdueGreenEdge GroundsMaintenance
Lift LOLER inspection6-monthly25 Dec 202525 Jun 2026Due soonPinnacle Lift ServicesLOLER 1998
Fire alarm service6-monthly2 Jan 20262 Jul 2026Due soonSafeGuard Fire ConsultantsBS 5839
Emergency lighting testAnnual20 Aug 202520 Aug 2026On trackBrightSpark ElectricalBS 5266
Buildings insurance certAnnual1 Sep 20251 Sep 2026On trackSterling Insurance BrokersRICS 4th ed §9
D&O / liability insuranceAnnual1 Sep 20251 Sep 2026On trackSterling Insurance BrokersGood practice
Fire Risk Assessment certAnnual15 Oct 202515 Oct 2026On trackSafeGuard Fire ConsultantsRICS 4th ed §10 / RRO 2005
Health & safety risk assessmentAnnual15 Oct 202515 Oct 2026On trackSafeGuard Fire ConsultantsHSWA 1974
Asbestos management review certAnnual30 Nov 202530 Nov 2026On trackSafeGuard Fire ConsultantsCAR 2012
Legionella / water risk2-yearly15 Jan 202515 Jan 2027On trackSafeGuard Fire ConsultantsACOP L8
EICR (communal) cert5-yearly1 Mar 20231 Mar 2028On trackBrightSpark ElectricalBS 7671
EWS1 / external wall assessmentNot required — building is 4 storeys / ~13.5m, below the 18m threshold and not high-risk.As requiredNot applicableBuilding Safety Act 2022
EWS1 / external wall assessment: not currently required — Wadebridge Court is 13.5m (below the 18m threshold) with no relevant cladding. Reeve will re-flag this if building-safety guidance changes.